#06 VERN' Consortium Meeting-15-16 November 2017

Meeting Objective

Financial, Towards Midterm report, SinnoLab models presentation, WP Status, Feedback from Training

Agenda

Day 1 - 15/11/2017 – Wednesday

12:30:13:00   Registration
13:00-13:30   Opening - Welcome to VERN’ University
13:30-14:30   Lunch (paid from institutional per diem)
14:30-14:50   Session 1

P04 Tel-Hai: Project management and coordination (WP5):

  • Travel report
  • Timesheets
  • Equipment

14:50-15:10   P04 Tel-Hai: Tel-Hai innovation index from the mapping of the student coopetition (WP1)
15:10-15:30   P03 Sapir: Dissemination work plan (WP4)
15:30-15:50   P13 Vern – Zagreb: Training Managers Plan (WP2)
15:50-16:00   Discussion
16:00-16:15   Coffee Break
16:15-16:35   P14 IST-Lisbon: Training Teachers Plan (WP2)
16:35-17:20   Mid Term Report - Financial report
17:20-17:45   Mid Term Report- Narrative report
17:45-18:30   Workshop
               18:30    End of Day 1
19:00-21:00   Dinner
The dinner will take place at “Klub Papica” or CookingCroatia- also a social innovation project where mother and son cook in their authentic old Zagreb apartment traditional Croatian meals The dinner would cost approximately 20-25 EUR. Please find more information on http://cookingcroatia.com/en/

Day 2 - 16/11/2017 – Thursday

09:00-09:15   Registration
09:15-09:45   Session 2
P04 Tel-Hai: Start of the planning of the second year on local and international level (WP5)
09:45-10:30   P02 Quality Plan – Work plan, team, framework (WP3)
10:30-11:00   Relations and partnership between SinnoLABs host organisations and third party structures and stakeholders for sustainable collaboration (WP2)
11:00-11:15   Coffee Break
11:15-12:00   Workshop - SinnoLABs model and work plan
12:00-12:30   Good practices and lessons learned from the workshop
12:30-13:30   Lunch (paid from institutional per diem)
           13:30   End of Day 2

Summary

During both days, the following topics were presented. Each field leader exhibited a detailed presentation on the topic, the WP progress and suggestions for further advancement:

  • Transferring the coordinator from IDC to Tel Hai.
  • SinnoLAB infrastructure and equipment purchasing delay
  • Economic management of travels and filling out travel reports
  • My approval for the projects diagnosis to be submitted to the Parfrieden SinnoLAB WP1.
  • Quality assurance Plan Approval- wp3

 

ACCOMMODATION

BUDGET CONSIDERATION

Travel & Meeting Venue

VERN\' University